PROJECT SCHEDULE

JUNE 2020

Design Build Request for Proposals due from the 3 design build teams.

AUGUST 2020

Award Design Build Agreement

OCTOBER 2020

CONSTRUCTION BEGINS - DEMOLITION

NOVEMBER 2020

SITE WORK/ROUGH GRADING

APRIL 2021

FOUNDATION/SUBSTRUCTURE

MAY 2021

BUILDING STRUCTURE/EXTERIOR

NOVEMBER 2021

SITE IMPROVEMENTS

MARCH 2022

SUBSTANTIAL COMPLETION

JUNE 2022

GRAND OPENING