top of page

PROJECT SCHEDULE
JUNE 2020
Design Build Request for Proposals due from the 3 design build teams.
AUGUST 2020
Award Design Build Agreement
OCTOBER 2020
CONSTRUCTION BEGINS - DEMOLITION
NOVEMBER 2020
SITE WORK/ROUGH GRADING
APRIL 2021
FOUNDATION/SUBSTRUCTURE
MAY 2021
BUILDING STRUCTURE/EXTERIOR
NOVEMBER 2021
SITE IMPROVEMENTS
MARCH 2022
SUBSTANTIAL COMPLETION
JUNE 2022
GRAND OPENING
bottom of page